| Stage 1: Scrap operations |
| • |
Scrap
is collected and screened for radiation |
| • |
Scrap
is further processed by sorting, shearing and shredding |
|
 |
| Stage 2:
Meltshop – Melting process |
| • |
Scrap
is screened for radiation again |
| • |
Scrap
is melted using the electric arc furnace |
|
 |
| Stage 3:
Meltshop – Chemistry refinement and temperature
control |
| • |
Molten
steel is transferred to the 80-tonne Ladle Furnace for
chemistry refinement and temperature control |
|
 |
| Stage 4:
Meltshop – Continuous casting |
| • |
Refined
molten steel flows to this machine with a 5-strand high
speed caster |
| • |
Billets
are cast from it |
| • |
The
billets are directly hot charged to the rolling mill,
resulting in fuel oil savings |
|
 |
| Stage 5:
Bar & wire rod production at the rolling mill |
| • |
Automated
process where billets are rolled into reinforcement bars
and wire rods |
| • |
Rolling mill has a
capacity of 1 million tonnes per annum
|
| • |
Fast design
speeds of 30m/s for 10mm diameter rods and 100m/s
for 5.5mm diameter rods |
| • |
Precise tolerance
control using a six-pass bar block |
|
Upstream Products
| • |
Reinforcement
bars |
| • |
Wire rods |
|
|
| Make
a selection: |
 |
 |
|
|
|
|